July 29, 2006



This was a grueling day. Everything seemed to take longer than expected. The plan for today was to get the roof finished. My carpenter was skeptical that we would get that done. He was right. This was a lot more work than both of us expected. We did complete the installation of the roof sheathing, but the fascia board was the most critical and time consuming. The plans had no details on the fascia board. I'm glad I had a carpenter. He determined a method using 1x12 fascia board.



















The fascia board at the eaves were made from 1x12 planks.