Tuesday, September 12, 2006

September 10, 2006






I had to attend a funeral on Saturday so I rescheduled the carpenter for Sunday. We accomplished quite a bit of work with additional help from a neighbor. We foresee the end coming soon. We re-installed the two upper windows because it needed the Tyvek wrap and T1-11 siding. (These windows were previously placed temporarily just to see how it would look.) Also notice the flashing added between the siding and the roof shingles.









We completed the T1-11 siding at front. It will be primed very soon. The soffits still need to be finished.













We installed two more windows on another wall and completed the Z-flashing at the bottom of the T1-11 siding. Caulk will be applied between the concrete pad and the Z-flashing to complete the seal at the bottom.







The French Double Door was a three-person job to install.